The old ventilation unit was replaced with a new heat recovery system equipped ventilation unit. The efficiency of machines is at least 70%. The motivation for the project was to improve the conditions and save energy.
Kindergarten of lakso in ii
Kuivaniemi nursing home in Ii The target building roof had previously been covered with a thick layer of ice inside roof structure. […]
• In the background, the councils group initiative to improve public transport • The topic is also supported by a survey conducted […]
The street lighting control of the entire municipal area was renewed, totaling 65 control centers. The renewal of the control will enable […]
In the approximately 100m long corridor, the previously time-controlled (7-19) T8 fluorescent tubes were replaced with LEDs and a smart control was […]